L.C. Energy Ltd.
Designed By:
Gorkhasoft Pvt. Ltd.
Email: softgorkha@gmail.com
Home
Documents
Salient Features
Main Report
Drawings
Legal Documents
Company Audit Reports
Status
Completed
In Progress
Budgetwise Expenses
Equity/Bank Loan
Work Progress
Summary Sheet
Progress Report
Site Progress
Civil Works
Hydromechanical Works (Phase-I)
Hydromechanical Works (Phase-II)
Electromechanical Works
Transmission Line
News
Organization
Board of Directors
Member Login
Project Info
Contact
General
Equity Investment
Gmail Login
Civil Works
Today's Progress:
Concrete @Final stage of surgetank in progress
Cable duct inside powerhouse in progress
Beam @ control room area in progress
Block wall @Powerhouse is in good progress
Surgetank form work for final stage completed
Wall works @Powerhouse in progress
Wall @ powerhouse in progress
Wall @ powerhouse in progress
Wall @ powerhouse
Cable duct @ powerhouse in progress
Wall works @ powerhouse in progress
Work @ control room area in progress
Finishing works @Powerhouse in progress
Block wall @ Powerhouse in progress
Surgetank works in final stage
SP @ headrace alignment in progress
Generator pad concrete works in progress
Surgetank works at the end
Control room area works in progress
Control room area works in progress