L.C. Energy Ltd.
Designed By:
Gorkhasoft Pvt. Ltd.
Email: softgorkha@gmail.com
Home
Documents
Salient Features
Main Report
Drawings
Legal Documents
Company Audit Reports
Status
Completed
In Progress
Budgetwise Expenses
Equity/Bank Loan
Work Progress
Summary Sheet
Progress Report
Site Progress
Civil Works
Hydromechanical Works (Phase-I)
Hydromechanical Works (Phase-II)
Electromechanical Works
Transmission Line
News
Organization
Board of Directors
Member Login
Project Info
Contact
General
Equity Investment
Gmail Login
Civil Works
Today's Progress:
Flooring inside Unit-1 and unit-2 completed
Control room roof slab rebar works completed
Rebar work @ AB and SP at headrace line
AB rebar at headrace line in progress
Construction of surgetank completed
Saddle pier at headrace in progress
Construction of saddle at headrace in progress
AB47 @ headrace rebar in progress
Powerhouse flooring is going to complete
AB46 ready for concrete
Material stocking is also in progress
Work @ control room slab in progress
Concrete @powerhouse floor in progress
Excavation work @ headrace is in progress
Floor slab inside powerhouse near to complete
Control room work @Powerhouse in progress
Support pier work at headrace in progress
AB and Support pier @ headrace line in progress
Rebar @AB at headrace in progress
Excavation work @ headrace line in progress