L.C. Energy Ltd.
Designed By:
Gorkhasoft Pvt. Ltd.
Email: softgorkha@gmail.com
Home
Documents
Salient Features
Main Report
Drawings
Legal Documents
Company Audit Reports
Status
Completed
In Progress
Budgetwise Expenses
Equity/Bank Loan
Work Progress
Summary Sheet
Progress Report
Site Progress
Civil Works
Hydromechanical Works (Phase-I)
Hydromechanical Works (Phase-II)
Electromechanical Works
Transmission Line
News
Organization
Board of Directors
Member Login
Project Info
Contact
General
Equity Investment
Gmail Login
Civil Works
Today's Progress:
Surge tank work in progress
Powerhouse work in progress
Powerhouse work in progress
Penstock AB work in progress
Penstock support pier work in progress
SP at penstock line are in progress
Backfill @ surge tank in ptogress
Final level column for truss is in progress
Crane beam at powerhouse completed
Crane beam at powerhouse is completed
Crane beam at powerhouse is completed
Support pier @ headrace alignment
Support piers @ headrace alignment
Retaining wall @AB6
SP works in progress
Concrete @ surge tank
Base slab @ structure completed
Embedded plate at Crane beam in progress
Super structure @ Powerhouse in progress
Embedded plate at Crane beam in progress